2015-02-10 - 8009.1300 - Rel Notes - EMEA POS Extract #SAPReleaseNotes
Release Notes - Draft
8009.1300 - EMEA POS Extract - Update Extract when ZMRP Price updated
Admin Info
Purpose
|
Update Extract when ZMRP Price changes are made
|
Release No
|
003
|
Submitted on
|
02/10/2015
|
Submitted by
|
Siba Mohapatra
|
Environment
|
NECNED to NECNEQ
|
Sent To
|
Craig Spangler
|
Object(s) created by
|
Venkat Kondapally
|
Object(s) tested by
|
Siba Mohapatra/ Surya Basa
|
Transport Status
|
Created in NECNED100
|
Transport and Technical Objects
Sl.
|
Transport ID
|
Description
|
Object Name
|
1
|
NEDK928828
|
SD: 8009: XML Inventory O/P-Chnge of logic for ZMRP Price updt
|
ZIMM_XML_INVENTORY_OUTPUT
|
Release Notes
For Infrastructure
NA
For Requestor
Below is the previous transport.
- NEDK928357 - SD:8009:Cost field logic change and currency conv.(GBP - EUR)
- NEDK928700 - SD:8009:Consider valid season and msglog missing data
Test Notes
System : NECNED500
Below are the test data prepared in NECNED 500.
Test ID
|
Test Scenarios
|
Expected Results
|
Actual Results
|
P/F
|
Tested By
|
QA By
|
SD0001
|
Update the ZMRP price for a material - 10916418 (Plant-0325, Sorg-2000). And Execute the program with the date input and reatil orders check box ,with below inputs. 2000 sales org ,customer 1000018,currency EUR and plant 0325 in the selection screen.
|
The material - 10916418 should display in program output and Extract file.
|
Material - 10916418 displayed in program output and Extract file.
|
P
|
Siba Mohapatra
|
Surya Basa
|
SD0002
|
Delete the ZMRP price and COST for material- 70099089 (Plant-0325, Sorg -2000). And Execute the program with the date input and reatil orders check box ,with below inputs. 2000 sales org ,customer 1000018,currency EUR and plant 0325 in the selection screen.
|
The material - 70099089 should display in program output and it should not display in Extract file.
|
The material - 70099089 displayed in program output and it did not display in Extract file.
|
P
|
Siba Mohapatra
|
Surya Basa
|
SD0003
|
Update only COST change for material -10964086 (Plant-0325, Sorg-2000). And Execute the program with the date input and reatil orders check box ,with below inputs. 2000 sales org ,customer 1000018,currency EUR and plant 0325 in the selection screen.
|
The material - 10964086 should not be displayed in program output and Extract file.
|
The material - 10964086 not displayed in program output and Extract file.
|
P
|
Siba Mohapatra
|
Surya Basa
|
SD0004
|
Update the COST with Material description for Material- 80039709. Where ZMRP is already updated. And Execute the program with the date input and reatil orders check box ,with below inputs. 2000 sales org ,customer 1000018,currency EUR and plant 0325 in the selection screen.
|
The material- 80039709 should be displayed in program output and Extract file with updated COST.
|
The material- 80039709 displayed in program output and Extract file with updated COST.
|
P
|
Siba Mohapatra
|
Surya Basa
|
Below are the Extract files and Screen shots for the above tests.
SD0001:
ZMRPchange.xml
SD0002:
ZMRP_COSTdeleted.xml
SD0003:
COSTchange.xml
SD0004:
COST_MATDES.XML
System: NECNEQ100
NA
Reference Document (Specification or Production Support Break Fix)
SD-Deepak - Venkat - 2015-01-05 -8009.1300 - Spec - EMEA POS Extract - (Craig by 2015-01-16)